Fuse Rail

Scope: Fuse Rail have been undertaking works within Depots and Sidings throughout Kent and Sussex. The project scope was to make modifications to conductor rails in order to help minimise the risk to walkway users.  In addition, we have replaced HV feeder cable route containment, installed new walkways, refurbished existing walkways and installed handrails to help maintain the safe walking routes.

Fuse Rail

Highlights:

  • 200 metres of walkways and crossings
  • 130 conductor rail cut backs away from existing walkways
  • 960 metres of DC cabling
  • 2400 metres of guardboarding
  • 200 metres of GRP handrails